| THE GSLC LSL CLASSROOM EXPANSION 2012 | ||||||
| PROJECT TIMELINE | ||||||
| DESCRIPTION OF WORK | DURATION | START | COMPLETION | % OF PROJECT | 12 ft Addition | 16ft Addition |
| Site (demo shed, porch roof, haul) GSLC/LSL | 2 days | April 13th | April 14th | 2% | $352.98 (credit) | $474.16 (credit) |
| Prep | 7 days | May 1st | May 9th | 5% | $882.45 | $1,185.39 |
| Foundation forms | 2 days | May 14 | May 15 | 6% | $1,058.94 | $1,422.47 |
| Inspection (Foundation) | 1 day | May 16 | May 16 | n/a | n/a | n/a |
| Pour concrete | 4 days | May 17 | May 22 | 10% | $1,764.90 | $2,370.78 |
| Framing | 3 days | May 23 | May 25 | 20% | $3,529.80 | $4,741.56 |
| Dry-In | 3 days | May 28 | May 30 | 20% | $3922.00 | $5268.40 |
| Exterior | 3 days | May 31 | June 4 | 10% | $1,764.90 | $2,370.78 |
| Demo Int. Wall | 1 day | June 5 | June 5 | 5% | $882.45 | $1,185.39 |
| Electrical Rough-In | 3 days | June 6 | June 8 | 5% | $882.45 | $1,185.39 |
| INSPECTION ELECTRICAL | 1 day | June 11 | June 11 | n/a | n/a | n/a |
| Interior drywall/molding | 8 days | June 12 | June 21 | 15% | $2,647.35 | $3,556.17 |
| Painting GSLC/LSL | | June 22 | June 24 | | $650.00 (Credit) | $758.00 (Credit) |
| Exterior | 1 day | June 22 | June 22 | 2% | $352.98 | $474.16 |
| Walk-Through | 1 day | June 25 | June 25 | n/a | | |
| Final Inspection/Certificate of Occupancy | 2 days | June 26 | June 27 | | | |
| Completion | | *July 6th | *July 6th | 10% | $1961.00 | $2634.20 |
| TOTAL | | | | | $19,610.00 | 26,342.00 |
| Fee Schedule: 25% Down payment 25% Framing complete 25% Utilities roughed-in 15% Interior finishes complete 10% Final inspection and C.O. issued | | |||||