Tuesday, March 27, 2012

GSLC LSL EXPANSION TIMELINE AND COSTS

THE GSLC LSL CLASSROOM EXPANSION 2012
PROJECT TIMELINE
DESCRIPTION OF WORK
DURATION
START
COMPLETION
% OF PROJECT
12 ft Addition
16ft Addition
Site (demo shed, porch roof, haul)   GSLC/LSL
2 days
April 13th
April 14th
2%
$352.98
(credit)
$474.16
(credit)
Prep
7 days
May 1st
May 9th
5%
$882.45
$1,185.39
Foundation forms
2 days
May 14
May 15
6%
$1,058.94
$1,422.47
Inspection (Foundation)   
1 day
May 16
May 16
n/a
n/a
n/a
Pour concrete         
4 days
May 17
May 22
10%
$1,764.90
$2,370.78
Framing
3 days
May 23
May 25
20%
$3,529.80
$4,741.56
Dry-In
3 days
May 28
May 30
20%
$3922.00
$5268.40
Exterior
3 days
May 31
June 4
10%
$1,764.90
$2,370.78
Demo Int. Wall      
1 day
June 5
June 5
5%
$882.45
$1,185.39
Electrical Rough-In
3 days
June 6
June 8
5%
$882.45
$1,185.39
INSPECTION ELECTRICAL
1 day
June 11
June 11
n/a
n/a
n/a
Interior drywall/molding
8 days
June 12
June 21
15%
$2,647.35
$3,556.17
Painting  GSLC/LSL

June 22
June 24

$650.00 (Credit)
$758.00
(Credit)
Exterior
1 day
June 22
June 22
2%
$352.98
$474.16
Walk-Through
1 day
June 25
June 25
n/a


Final Inspection/Certificate of Occupancy
2 days
June 26
June 27



Completion

*July 6th
*July 6th
10%
$1961.00
$2634.20
  TOTAL




$19,610.00
26,342.00
Fee Schedule: 25%  Down payment
                          25%  Framing complete
                          25%  Utilities roughed-in
                          15%  Interior finishes complete
                          10%  Final inspection and C.O. issued